The written scope should explain where these workstreams overlap.
Find the decision that is actually holding the job
A recovery project can feel stalled because the next action is described too broadly: “waiting for restoration” or “waiting for insurance.” Use this worksheet to identify the exact question, the evidence needed and the person responsible for answering it. Several workstreams can move at once; one completed box does not approve the next one.
For example, a repair may be waiting for a structural detail, a drying record or an agreed contents decision. Each needs a different handoff. Keep the dependency visible rather than assigning an unsupported finish date.
Use a decision-based sequence
| Stage | Evidence or answer to identify |
|---|---|
| Access | Current instruction, permitted areas and restrictions. |
| Assessment | Affected boundary, professional findings and unresolved areas. |
| Treatment | Written proposed method, exclusions and authorization. |
| Repair | Design, permits, trade work and inspections that apply. |
| Use and completion | Relevant reviewer, outstanding conditions and required records. |
This is a planning map. The responsible authority and qualified professionals make the property-specific decisions. Read how fire restoration works for the full explanation.
Build your decision and dependency map
Run a short project review
At each update, ask three questions: What new evidence arrived? Which decision does it resolve? What is the next unanswered question? Record changes as dated entries. If the answer comes from another person, identify that person and the document or message rather than presenting it as your own assessment.
Download a copy before leaving the page. Preparing or downloading the map does not send it to HAUSE. The optional enquiry handoff preserves the fields for another editable review.
Sources and further reading
Reviewed October 11, 2026. Follow the source’s current guidance and the instructions for the actual property.